Q Question 1 10 / 10 pts After constructing a project network based on technical constraints and reviewing resource requirements throughout the project, Anne realizes many peaks and valleys in regard to resource usage. At one point Anne needs 6 developers, but top management has made it very clear that she will not have access to more than 4. Classify Anne's project in terms of her scheduling problem. What are her options at this point? Your Answer: Question 2 10 / 10 pts What is the difference between functional conflict and dysfunctional conflict on a project? Provide real examples of each. Your Answer: Question 3 10 / 10 pts Identify and briefly describe two of the five strategies to manage dysfunctional conflict.